KFC prototype Ground up complete new build/site work scope of work with an accelerated schedule. The new design incorporated a retro 60’s design with the new kitchen requirements, bullet resistant wall shielding and glass for the protection of the staff in a distressed area of Detroit MI. The site had existing soils that could not bear the new footings for the building which required a re-engineering of footings to a non-standard design causing severe delays to an accelerated project. The project was completed on time and opened before the new year meeting the requirements set forth per the contract terms and with KFC corporate. The client was extremely happy with the completion of the project with many obstacles and still maintaining quality and budget.